Route, Constructability, ITB
Some of the challenges:
-
Minimizing equipment handling.
-
Defining equipment installation sequence (120T~470T equipment)
-
Scope of Work development
Solution:
-
Proposed heavy haul route.
-
Redesign steel structure to enable usage of lift frame.
-
ITB, RFQ and Technical Scoring Matrix
HL/HH Planning & Budgeting
Some of the challenges:
-
Planning and budget analysis of the structure to determine HL/HH strategy. Transport and install fully or partially assembled. (~ 135T)
​
Solution:
-
Performed scenario analysis integrated with client team.
Levee Crossing
Some of the challenges:
-
Delivery of 700T vessel near Mississippi River jobsite.
Solution:
-
Levee Crossing. Provided all engineering and permit coordination.
HL/HH Management
Some of the challenges:
-
Onsite management of all HL/HH and barging activities.
Solution:
-
Provided fulltime HL/HH Manager along with inhouse engineering backup. Daily reporting to client with monthly cost savings overviews.
Turnaround Support
Some of the challenges:
-
Defining TAR crane requirements, Maximize efficiency
Solution:
-
Defining TAR HL requirements, including crane sizes, placement, crane pads.
-
Overseeing and coordination of all HL activities during TAR
Turnaround Support
Some of the challenges:
-
Minimize 65T condenser change out critical path duration.
-
Minimize removal of obstructions.
Solution:
-
Proposed unique jack-and-slide solution in combination with HH/HL.
Engineering Solutions
Some of the challenges:
-
Provide a solution to exchange 200 reformer tiles. Eliminate cumbersome individual bull-rigging scenarios.
-
Minimize turnaround critical path duration.
Solution:
-
Track design with multiple gantries.
Engineering Solutions
Some of the challenges:
-
Provide a lightweight lift system in congested site area.
-
Avoid removal of site obstructions.
Solution:
-
Designed and fabricated a lightweight aluminum modular gantry.
Engineering Solutions
Some of the challenges:
-
Providing safe and quick access to perform full internal Sphere Inspections.
-
Minimize turnaround critical path duration.
Solution:
-
Designed and fabricated an aluminum rotating access system (reduced installation from 30 days to 4 days)